The Supreme Court has restored an arbitration award for additional dredging work at Sagar Island, holding that a court cannot halve an evidence-backed award simply because the claim exceeds 70% of the original contract value. A government entity receives no special protection from an otherwise valid monetary award.

New Delhi: The Supreme Court on November 18 set aside a Calcutta High Court decision reducing an arbitration award to 50% of the amount determined by the arbitrator, rejecting the view that the size of the additional-work claim, by itself, shocked the court’s conscience [M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata].
The Bench of Justices J.B. Pardiwala and K. Vinod Chandran restored the award in the contractor’s favour. Justice Chandran authored the judgment, which applies the limited scope of appellate interference under Section 37 of the Arbitration and Conciliation Act, 1996.
Why the additional work became disputed
The contract concerned dredging an approach channel and basin for a shore-based pilot station at Sagar Island. The judgment records that adverse weather and a mismatch between actual soil conditions and the data supplied by the Port Trust necessitated additional work. A letter dated July 19, 2000 supported the entrustment of that work.
The original work was valued at Rs 2,86,56,200, of which Rs 2,79,32,865 had been paid. The arbitration concerned additional work. The award dated November 3, 2003 survived the Port Trust’s Section 34 challenge before a Single Judge.
In appeal, however, the High Court’s Division Bench cut the quantified amount by half and reduced interest to 6% on the principal sum from February 8, 2002. It did so despite finding that the award rested on relevant evidence and was neither perverse nor patently illegal.
A large claim needs a legal objection, not a percentage cut
The contractor argued that the High Court had substituted a subjective reaction to the bill for the statutory grounds of interference. The Port Trust sought to have the entire award set aside or, alternatively, to retain the reduction.
Rejecting the reduction, the Supreme Court explained in paragraphs 7 to 10 that the additional work involved re-dredging of the same kind as the original contract. Its value exceeding 70% of the original work did not establish a conflict with basic notions of morality or justice. The invocation of judicial conscience required a substantive reason rooted in the recognised legal standard.
The Court also noted that the Port Trust’s failure to issue a completion certificate did not, in the circumstances recorded by the High Court, defeat payment for work supported by measurements and other relevant documents.
No basis to split the award into valid and invalid parts
Applying Gayatri Balasamy v. M/s ISG Novasoft Technologies Limited, 2025 INSC 605, the Bench distinguished permissible partial setting aside from the arbitrary reduction made here. Paragraphs 11 and 12 explain that the measurements and invoices concerned the same additional dredging work and could not be separated into valid and invalid components.
Paragraph 13 further rejects preferential treatment merely because the award debtor is a government entity. An apparent excess in the amount, unsupported by a valid objection to the award, was insufficient.
The result
The contractor’s appeal was allowed and the arbitral award restored. The Port Trust’s connected appeal was disposed of because the impugned judgment had already been set aside. The decision reinforces that Section 37 does not permit a court to replace an arbitrator’s evidence-based calculation with its own impression of an acceptable price.
Case Title: M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata
Case Numbers: Civil Appeal Nos. 14303 and 14304 of 2026
Citation: 2026 INSC 1238
Court: Supreme Court of India
Bench: Justices J.B. Pardiwala and K. Vinod Chandran
Date of Judgment: November 18, 2026
Status: Final judgment; contractor’s appeal allowed, award restored; Port Trust’s appeal disposed of