Supreme Court Restores Power Grid’s Tuticorin Transmission Charges, Holds Generator Liable For Delayed Dedicated Line

4 min read

The Supreme Court has restored CERC’s order permitting transmission charges for Power Grid’s Tuticorin pooling-station links, rejecting APTEL’s finding that the assets had not been used. The generating company’s delay in commissioning its dedicated transmission line justified the liability imposed for the intervening period.

Supreme Court of India building, which restored transmission charges for Power Grid’s Tuticorin pooling-station links

New Delhi: The Supreme Court on November 18 allowed Power Grid Corporation of India Limited’s appeals in a dispute over charges for two transmission links at the Tuticorin Pooling Station, setting aside the Appellate Tribunal for Electricity’s orders and restoring the Central Electricity Regulatory Commission’s decision [Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors.].

The Bench of Justices J.B. Pardiwala and K. Vinod Chandran held that the links had carried electricity and that their approved commercial operation dates did not require reconsideration. Justice Chandran authored the judgment.

What the tariff dispute concerned

The assets were two Line-In Line-Out, or LILO, links connecting the circuits of the Tuticorin JV–Madurai transmission line to the pooling station. They became commercially operational on January 4 and January 8, 2015 respectively.

The generating company, now Moxie Power Generation Limited and formerly Coastal Energen Private Limited, had an obligation to build its own dedicated transmission line to the pooling station. That line became operational on October 27, 2016. The disputed claim concerned the period between the LILOs’ commissioning and that date.

APTEL had considered non-Point of Connection charges of Rs 15,43,26,909. It accepted that the LILOs were permanent components of the transmission plan but found that they had not been used and required reconsideration of their commercial operation dates.

Delay on another route did not mean these assets were idle

The generating company and TANGEDCO relied on the delayed completion of onward transmission infrastructure towards Salem and Madhugiri. They contended that the pooling-station links could not attract the disputed charges before the larger arrangement became operational.

The Supreme Court rejected that account of the electricity’s route. Examining the transmission plan, diagram and agreements, it found that the LILOs diverted power through the Tuticorin Pooling Station and returned it to the Tuticorin JV–Madurai line for onward transmission. The delay on the Salem route did not prevent this arrangement from operating.

Paragraph 16 also records the generating company’s own earlier acknowledgement that the assets were being used, coupled with a request that charges be shared through the Point of Connection mechanism. The Court held that sharing could not be claimed without commissioning the dedicated line.

Commercial operation dates were already properly accepted

The Bench distinguished assets prevented from entering regular service from assets actually operating after successful trials. In paragraphs 39 to 41, it found that the special approval mechanism under Regulation 4(3)(ii) of the 2014 Tariff Regulations did not require a fresh determination here.

CERC had accepted the January 2015 dates on the strength of the Regional Load Despatch Centre’s successful-trial certificate and the Central Electricity Authority’s safety certificate. Actual transmission had continued, and the Court found no basis to reopen those dates.

Liability followed the delayed dedicated connection

The judgment upholds CERC’s allocation of liability to the generating company for the period before its dedicated line was established. Paragraph 34 records the underlying arrangement: 50% of the LILO charges were to enter the Point of Connection pool, while the remaining 50% were to be borne by the generator that had not commissioned its dedicated line.

The Court also cautioned against reading a party’s submission as the regulator’s conclusion. Paragraph 48 explains that the passage in CERC’s order relied upon by APTEL recorded TANGEDCO’s contention; the succeeding reasoning imposed liability on the generating company.

Allowing the appeals, the Court restored CERC’s order. The decision ties transmission-charge liability to the assets’ actual operation, the approved contractual arrangement and the generator’s delayed dedicated connection.

Case Title: Power Grid Corporation of India Limited v. Tamil Nadu Generation and Distribution Corporation Limited (TANGEDCO) & Ors.
Case Numbers: Civil Appeal Nos. 14780–14781 of 2025 with Civil Appeal No. 13153 of 2026
Citation: 2026 INSC 1237
Court: Supreme Court of India
Bench: Justices J.B. Pardiwala and K. Vinod Chandran
Date of Judgment: November 18, 2026
Status: Final judgment; appeals allowed, APTEL orders set aside and CERC order restored