Before it decides MMRDA’s plea for mangrove clearance for an elevated pod car corridor in Bandra-Kurla Complex, the Bombay High Court has asked Maharashtra for five years of green-cover and sapling-survival data, remarking that “everything is on paper”.

Mumbai: “Why not show in advance the bonafide genuine effort?” the Bombay High Court asked on Wednesday, November 25, 2026, while hearing the Mumbai Metropolitan Region Development Authority’s plea to divert 0.2869 hectares of mangrove forest land for an 8.85-km elevated Automated Rapid Transit System, a driverless electric pod car network, in Bandra-Kurla Complex [MMRDA v. Union of India].
The oral remarks came from a Bench of Chief Justice Mahesh Chandra Tripathi and Justice Advait M. Sethna, which told State agencies that tree plantation cannot be treated as a paperwork formality while green cover is cleared for infrastructure, and that afforestation should begin before, not after, they seek the Court’s permission. No order on the plea has been passed yet, and the Court has not ruled on the merits.
Data first, orders later
The Bench asked the State to place on record concrete data for the past five years on total green cover, losses and sapling survival rates before the Court passes orders. “We are not against the project. However, we do not want to move till compliance is seen,” it said. The matter is listed on November 30.
What MMRDA seeks
MMRDA approached the Court under the High Court’s 2018 judgment protecting Maharashtra’s coastal wetlands, which requires explicit court permission, in the larger public interest, before any development affecting mangroves can proceed. According to the authority, no mangroves will be felled for the project, six trees fall in the alignment, and it has undertaken to plant 100 trees as compensation.
Advocate Saket Mone, for MMRDA, said the elevated corridor is vital for last-mile connectivity and that plantation is the Forest Department’s responsibility rather than that of the construction agency.
The Bench’s questions
The Bench wondered why compensatory measures were not started as soon as the project was conceived:
“Greenery should be maintained. It will take some time for trees to grow. Once this project is coined by the authority, why are efforts to maintain the ecosystem not taken by authorities in advance, instead of putting stringent conditions for later? Why not show in advance the bonafide genuine effort?”
On the distance between filings and the ground reality, the Court remarked:
“If 30% cover is required, then how can we accord permission? Everything is on paper. But effectively nothing has happened for planting trees.”
Saline land and the monsoon
Advocate General Milind Sathe told the Court that a shortage of suitable saline land delays mangrove plantation, and that saplings are planted before the monsoon to improve survival.
What the hearing signals
Under the 2018 wetlands judgment, every Mumbai project touching mangroves must pass through the High Court. By asking for verifiable survival data rather than plantation undertakings, the Bench signalled that compensatory afforestation will be judged on results on the ground before fresh clearances are granted, a standard that could shape how other infrastructure agencies frame their applications.
Case Title: MMRDA v. Union of India
Bench: Chief Justice Mahesh Chandra Tripathi and Justice Advait M. Sethna, Bombay High Court
Date of Hearing: November 25, 2026 (next listed November 30, 2026)
Appearances: Advocate Saket Mone, briefed by Advocate Fatema Ansari, for MMRDA; Advocate General Milind Sathe, briefed by Additional Government Pleader Onkar Chandurkar, for the State