LawChakra

Homebuyers Can Demand Full Refund & Interest for Delayed Possession, Even If the Builder Agreement Says Otherwise: Supreme Court

The Supreme Court ruled that homebuyers can claim a full refund with interest for unreasonable project delays, even if the builder-buyer agreement states otherwise. This landmark judgment strengthens consumer rights against unfair real-estate contracts.

Thank you for reading this post, don't forget to subscribe!

Homebuyers Can Demand Full Refund & Interest for Delayed Possession, Even If the Builder Agreement Says Otherwise: Supreme Court

NEW DELHI: Delayed possession of residential flats has become one of the biggest concerns for homebuyers in India. In a landmark ruling, the Supreme Court of India in Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan (2019) upheld the rights of consumers and strongly condemned one-sided builder-buyer agreements. The Court ruled that a homebuyer cannot be forced to take possession after an unreasonable delay and is entitled to a refund with fair compensation.

This case has become an important precedent for homebuyers who experience project delays and seek legal remedies.

Background of the Case

The dispute arose from a residential project named “Araya Complex” in Gurugram, where the buyer entered into an Apartment Buyer’s Agreement on 08.05.2012. The developer committed to obtaining the Occupancy Certificate within 39 months from excavation, with an additional grace period of 180 days.

Due to the excessive delay, the buyer filed a complaint before the National Consumer Disputes Redressal Commission (NCDRC) seeking a refund with interest.

What the National Consumer Disputes Redressal Commission (NCDRC) Held

The NCDRC held that since the builder obtained the Occupancy Certificate almost 3 years after the contractually promised date, the homebuyer could not be compelled to take possession at such a belated stage, and therefore was entitled to a refund of the entire deposit with 10.7% simple interest, because the clauses relied upon by the builder were wholly one-sided and unfair.

The Court specifically notes that:

“the last date stipulated for construction had expired about 3 years before the Occupancy Certificate was obtained, [therefore] the Respondent – Flat Purchaser could not be compelled to take possession at such a belated stage… The clauses in the Agreement were held to be wholly one-sided, unfair, and not binding on the Respondent – Flat Purchaser.”

Arguments Presented by the Parties

Builder’s Defence

The developer argued that:

Buyer’s Position

The buyer insisted on a refund because:

Judgment of the Supreme Court

The Supreme Court upheld the NCDRC’s decision and ruled firmly in favour of the homebuyer. The Court held that the builder had failed to fulfill contractual obligations and committed a deficiency in service by delaying possession for years. As the Court observed:

“The inordinate delay in handing over possession of the flat clearly amounts to deficiency of service.”

The Court further emphasised that the buyer could not be forced to accept possession after such prolonged delay:

“The Respondent – Flat Purchaser… cannot be compelled to accept the possession whenever it is offered by the Builder.”

On the issue of exploitative contract terms, the Supreme Court made a strong finding that one-sided clauses in builder-buyer agreements cannot be used to defeat consumer rights:

“The contractual terms of the Agreement… are ex-facie one-sided, unfair, and unreasonable.”

Accordingly, the Court confirmed that the buyer was entitled to a refund of the entire amount deposited along with fair compensation, rejecting the builder’s attempt to deny interest:

“The National Commission has rightly awarded Interest @10.7% S.I. p.a.”

In conclusion, the Supreme Court dismissed the builder’s appeal, affirmed NCDRC’s order, and directed the builder to refund the amount within three months.

Appearance:
Appellant (Builder): Mr. C.A. Sundaram, Senior Counsel
Respondent (Flat Purchaser): Mr. Sushil Kaushik, learned Counsel

Case Title:
Pioneer Urban Land & Infrastructure Ltd. Versus Govindan Raghavan
CIVIL APPEAL NO. 12238 OF 2018

READ JUDGMENT

Click Here to Read Our Reports on Homebuyers

FOLLOW US ON YOUTUBE FOR MORE LEGAL UPDATES

Exit mobile version